Welcome
This page explains how to manage the list of Project Results in Beneficiary module. Project Results are the tangible results of a project, such as curricula, pedagogical materials, open education resources, IT tools, analyses, studies, methods, etc.
These can be accessed via the Project Results tab in your project.
The Project Results screen allows beneficiaries to list all the Project Results of their project as well as to detail the cost of production according to the different types of resources required to produce those Project Results.
The Project Results already approved by the National Agency in their management system will be displayed in this list when the project becomes available, with all amounts set to 0 (zero). These items can be edited to update the amounts.
The Project Results section of your project can be accessed from the Content menu. The Project Results screen contains a list of Project Results (1), if any are available.
Project Results already approved by the National Agency in their project management system will be displayed in this list, with all amounts displayed in the list set to 0 (zero). These results must be updated. See below for details.
Below the list you find information about the Total (Calculated) and Awarded Budget (2). The Total (Calculated) will be updated when results have been added or existing result updated. The Total (Calculated) can exceed the Awarded Budget. A scrollbar is available on the list to access all displayed information. See the page AGED List functionality in projects for additional information on the list options.
In our example, one Project Result was transferred from the NA project management system.
To add a Project Result to your project, click on the Create button.
The Project Result screen opens, consisting of the Project Result section (1) and the Organisations section (2) .
Take note
The Organisations section can only be completed once the Project Result details are completed and saved.
In the Project Result details section, provide the required information. Mandatory fields are marked with a red asterisk * .
When all mandatory information for the result is provided, the Save button at the bottom of the screen becomes active. Click on it to save your changes. A success message displays, confirming that the information has been saved successfully. Organisations can now be added.
Adding organisations is possible for newly created Project Results after they have been saved, as well as for the project results that have been transferred from the NA project management system, if any.
Click on the Create button in the organisations section of the Project Results.
Provide the required information. Mandatory fields are marked with a red asterisk * .
Additionally, two tick boxes, or flags, are available:
Force majeure is:
An unforeseeable exceptional situation or event beyond the participant's control and not attributable to error or negligence on their part.
Source: Erasmus+/European Solidarity Corps programme guides 2024, Glossary
Force majeure situations can arise anywhere and at any time, and include factors such as sudden disease, accidents, death, earthquakes and other causes.
In a project, check the Force majeure flag to indicate that a project activity (i.e. mobility activity, group activity, participations, events, transnational project meetings, etc.) is considered as a case of force majeure.
When you check this flag (tick box), certain fields and grants for the activity may be affected and must be checked and/or updated.
In addition, you must fill in the additional Force majeure explanations field, describing the facts that prove the activity should be accepted as a case of force majeure.
Organisations participating in Project Results having an end date within 2021 or later, the Force Majeure flag checked, and for which the provided Force Majeure Explanations contain keywords such as "corona" or "covid" (1) will automatically have the COVID-19 Affected flag set (2). It is not possible to tick the Covid-19 affected box manually.
The Total (Calculated) fields (3) for the available sections become editable and you can provide the total as per your needs.
Once all information regarding the organisation has been added, click on the Save button.
The organisation is now displayed in the list of organisations in the Project Result details. The Total (Calculated) below the list is updated. Follow the instructions above to add more organisations to the Project Result, if required.
Take note
The same organisation can only be added once per Project Result.
When all organisations have been added to the Project Result, click on the Return to list button.
The newly added Project Result is displayed in the list. All information provided for the result is available in the list view. The Total (Calculated) below the list is updated. Follow the instructions above to add more results to your project, if required.
Project Results that have been transferred from the NA project management system and that have been updated will display the updated values as per your changes.
See the page AGED List functionality in projects for additional information on the list options.