This page describes the steps to be taken to complete and submit the final beneficiary report for Erasmus+ projects. The steps described follow the example of using a project for action type KA105.
There may be differences between the beneficiary reports for different key actions but the basic functionality remains the same for each key action.
The project must be in follow-up status, unlocked and you must have the necessary permissions to modify the project data, in order to complete the Beneficiary Report.
Check the organisation details and associated contact persons for all organisations.
If any organisation details need to be updated, the National Agency should first be notified and the details should be updated in the Organisation Registration system. Once the changes are made in the National Agency's project management system, they will be reflected in Mobility Tool+.
This does not apply to certain contact details, such as those of the project co-beneficiaries and partners, which can be updated directly in Mobility Tool+.
Click the Mobilities tab to check that the mobility details are up to date. Any changes made to the mobility details will automatically update the budget summary.
Check the Budget tab to view the summary of the project budget as entered under each mobility.
Additional project costs may be entered in the budget tab depending on the action type. In the following example the Exceptional costs - Guarantee field can be edited. If you record additional costs in the Budget tab save the changes by clicking the Save button.
When all the project data is up to date, click the Reports tab and create the draft beneficiary report by clicking the Generate Beneficiary Report button.
Depending on the key action, you may see this button directly or you may need to navigate to the Final Beneficiary Report sub-tab to find the button.
Once you have generated the report, click on Edit Draft to access it. You will be directed tot the report screen. Note that the project status has now changed to processing.
In the top left corner of the report screen you will see:
Once you have started to fill in the report, if you leave the report screen you can return to it at any time by clicking on the Reports tab. You will have two options:
Click on the Show log + button on the Reports page to see the main actions performed on the report, and the person who performed each action. Click the Hide Log- button to close the log.
You will notice that the Context section is already filled in and marked with a green check.
The Context section contains the same information that is displayed under the project details (Details tab) and it cannot be modified in Mobility Tool+.
If project dates or titles require modifications this should be done by making a formal amendment request to the National Agency. Once this request is processed, the data will be updated in Mobility Tool+.
Navigate to the following sections by scrolling down or by clicking on the desired section in the left column of the report screen. The selected section is highlighted in blue.
As you fill in each section, it will be marked with a green check.
Click on the Project Summary section and add a summary for the project.
Remember that the project summary will be displayed in the Project Results Platform once the Final Report is finalised in the National Agency's project management system.
Information
Since 2016, a read-only copy of the summary provided at application stage is also included in the beneficiary report. It should be used as the base for the summary of the finalised project.
The summary is only requested in English, if the English version of the report is being used. For other language versions, the user needs to provide a summary in the language selected for the report and an English translation.
The application stage summary is also provided in both the specific national language and in English if the web application form was completed in a language other than English.
Remember that the project summary will be displayed in the Project Results Platform once the Final Report is finalised in the National Agency's project management system.
Once the next section Description of the Project is clicked, the previous section receives a green check mark, as all fields for that section have been completed.
In a similar way all other sections will be marked as completed.
Complete the section Implementation of the Project, detailing the practical arrangements and project management.
In the case of a long-term activity, complete the Linguistic Support section.
If this section is not applicable to the project, it is already highlighted with a green check or it may not appear at all. For other key actions this section will not appear.
In the Activities section, an overview of the activities and mobility flows are automatically inserted based on the budget outline.
You are also prompted to fill in organisational details of the organisation of planned activities.
In the Participants' Profile you will see a breakdown of the participants by activity, age, gender, sending organisation, etc. In addition, you are required to fill in details of the background and profile of the participants involved in the project and how they were selected.
The Learning Outcomes and Impact section prompts you to fill in details of learning outcomes acquired and/or improved by the participants and the impact of these outcomes.
The Impact section is only available for projects as of call year 2016. It requires you to provide further explanations about the impact of your project on the participants, the organisations and other stakeholders.
Provide details of the results of the project you would like to share together with descriptions of the activities carried out and target groups.
In the Future Plans and Suggestions section, indicate if you intend to continue cooperating with partners on future projects and provide further comments regarding this aspect.
The Budget section is automatically filled in with the Budget Summary, the Project Total Amount and Travel costs.
If the adjusted amount differs from the calculated amount, please provide an explanation.
Note that the Start Submission Process button at the top left side of the report screen is now available. This is because supporting documentation (Annexes) can also be added after you have started the submission process.
Click on Annexes and upload the supporting documentation as required.
The Declaration of Honour is mandatory for all projects and you must use the template provided with the report for each project:
Please note that according to national context, a signature may not suffice and a stamp for the organisation might be needed as well.
Repeat step 2 above to upload any additional required documents.
The uploaded files, including the declaration of honour, are listed in the List of uploaded files section.
However, you must mark the Declaration of Honour as such by clicking on Contains declaration of honour next to the correct file. The declaration is now highlighted in yellow and bears the mention DOH.
This is step is mandatory but it can also be performed after you have started the report submission.
Once all sections are completed, click on Start Submission Process.
Eventually you might not be able to submit the report, even if it is 100% complete. A warning message is displayed under the Start Submission Process button, informing you the mobilities are outdated and have to be revalidated. You will not be able to submit the report until this is done. The Start Submission Process button is inactive. Click on Revalidate Mobilities now to start the revalidation process. See MT+ Re-validation of mobilities for details on this functionality.
Once you have started the submission, the Beneficiary Declaration of Honour and Signature screen is displayed.
Here you can check that all of the required supporting documentation has been attached and Add more files if necessary.
If you did not mark the declaration of honour when you uploaded it, you must mark it at this stage.
Then, click the Next Step button to continue.
Read the Data Protection Notice and click Accept to continue.
A checklist appears prompting you to ensure that all actions have been performed.
As each item is checked, change the Not Done button to Done by clicking the respective button. Once all items are marked Done, click the Next Step button to continue.
To finish, click the Submit Beneficiary Report button. The project will be locked once the button is clicked.
A message is displayed indicating that the submission is in progress. It may take up to 15 minutes before the submission to the National Agency is completed.
Back in the Reports tab, you will be able to see when the report is successfully submitted. The project status displayed under the project number has also changed to submitted.
The project is now locked and can no longer be updated.