Zero Grant Extension flag


In KA171 project mobility activities, the Zero grant extension flag (1) is available in the Duration section of the mobility activity screen. This flag, once checked, indicates that the mobility activity was extended to a certain date and the extension period is not funded.

When the flag is ticked, the fields Extended Duration of Mobility Period (days), Extension duration (days) and Extension end date (2) become available.

Provide the Extension end date (3) as applicable. The Extended Duration of Mobility Period (days) and Extension duration (days) will be updated accordingly. There is no impact on the Duration calculated (days) or other Duration specific fields. 

Zero grant extension flag in KA171 mobility activities


Related Articles

Update the macro, i.e. replace label it_tools with module etc...